GADGET-2 portlet update (2)

GADGET-2 portlet update, Tuesday.

SitRep

@vale-anna gave a brief update of the situation, this morning, describing particularly the QA of the GUI; started a Travis integration;

Highlights are :

  • The goals have been re-shuffled a bit, we have two milestones now : “First Beta” and “First Beta of GUI”. The First Beta of GUI milestone is to give us a pat on the shoulder for a functional GUI, assure ourselves that it’s working and move onto backend integration with the GridEngine
  • We’ve added Travis integration, which is attempting to configure the entire runtime environment - Liferay, MySQL, GridEngine - for the portlet.

We’ll be having a scrum meeting at 15:40 to go over the GridEngine functionality and finish work on the GUI, moving to the actual implementation of the submission.

Feedback still required !

If you’re interested in the work, comment here, or request a feature on github